Heat pump grant — Fribourg
Flat amounts depending on heat pump type (air-water, ground-source).
Support from the canton of Fribourg and the Buildings Programme for heat pumps replacing fossil fuels.
www.leprogrammebatiments.chHeat pump installation · Villars-sur-Glâne

Small project
CHF 32'900 – CHF 60'300
Typical project
CHF 41'600 – CHF 77'500
Large project
CHF 54'600 – CHF 103'300
Computed with our estimator for Villars-sur-Glâne (regional factor included), standard finish. Only the project size changes.
3 °C. With 3472 heating degree days per year, your home's energy needs are significant. Anticipating the replacement of your fossil-fuel boiler before a total breakdown is crucial to maintaining thermal comfort without facing emergency situations.
The local building stock must adapt to the requirements of the Municipal Climate Plan adopted in October 2024. Opting for a heat pump reduces your dependence on fossil fuels and fulfills cantonal obligations.
By planning your work during milder seasons, you ensure optimal commissioning before the coldest days of the year arrive, while actively contributing to the municipality's energy transition.
The selection of your heat pump depends primarily on your plot configuration and the current insulation of your building. Air-water heat pumps are common but require special attention regarding noise levels towards neighbors, a major constraint in dense residential areas of Villars-sur-Glâne.
The choice between indoor or outdoor installation influences not only space requirements but also acoustic performance.
It is imperative to consider the local winter design temperature to ensure constant efficiency during the coldest days. Furthermore, before opting for a given power level, check if your area is connectable to the CAD Fribourg district heating network operated by Groupe E.
If connection is possible, it can be a relevant alternative. Finally, a well-dimensioned installation, coupled with potential optimization of your insulation, allows for achieving a high coefficient of performance over the long term.
The building stock in Villars-sur-Glâne presents a variety of eras that directly affect the installation of a heat pump. For houses built before 1990, special attention must be paid to the potential presence of asbestos in old pipe insulation during the removal of the fossil heating system.
In addition, these buildings often have less efficient thermal insulation, which requires a preliminary study to avoid oversizing the heat pump relative to actual needs.
Existing heat distribution networks, such as high-temperature radiators, may limit the efficiency of a modern heat pump. If your home dates from a period when energy efficiency was not a priority, it is recommended to couple the installation of the heat pump with measures to improve the building envelope.
A technical analysis allows evaluating whether the current network can be maintained or if it requires adaptation to operate with the more moderate temperature regime of a heat pump.
In Villars-sur-Glâne, replacing a fossil or electric heating system is governed by the Executive Regulation of the Cantonal Energy Law (RLE).
In force since January 1, 2024, this rule requires that at least 10% of the required heat be covered by renewable energy, or that equivalent energy-saving measures be carried out. This obligation applies specifically when replacing old fossil or electric installations.
Before starting work, systematically check local administrative procedures with the municipal technical department. If your building has historical or heritage value, additional constraints may apply, particularly regarding the visual integration of heat pump outdoor units.
Never begin work without receiving the necessary permits, and be sure to consult the Municipal Climate Plan for any additional specific requirements the municipality may have enacted beyond the current cantonal framework.
The canton of Fribourg offers grants for the installation of heat pumps, notably through the Building Program, to encourage the replacement of fossil fuel systems. Amounts are awarded as flat rates depending on the type of technology chosen (air-water, brine-water).
It is crucial to note that the subsidy application must be submitted imperatively before the start of the work. Any request made after the work has begun is inadmissible.
From a tax perspective, investments aimed at improving energy efficiency are deductible. For buildings older than 10 years, you can choose to deduct actual costs or apply a 20% flat rate of the rental value.
If your investments exceed your taxable income for the current year, the surplus can be carried forward to the two following tax periods. Consult the official Building Program website for details on the current amounts and specific conditions for granting these financial aids.
The completion of a heat pump project follows several structured steps, starting with a feasibility study and subsidy application before any equipment is ordered.
Once municipal authorization is obtained, the installation schedule is ideally organized outside of periods of extreme cold, although the installation can take place throughout the year.
The preparation phase includes ordering equipment and planning with installers to keep the heating interruption in your home to a minimum.
The project generally begins with the removal of the old fossil equipment, followed by hydraulic and electrical connection work. The installation of the outdoor unit, if applicable, requires minor masonry work for the base. Finally, commissioning, regulation tuning, and performance tests mark the end of the project.
It is advisable to plan these steps early enough in the year to avoid constraints related to frost days, thus ensuring a smooth and safe transition for your home.
Never neglect the thermal study of your building before choosing the power of your pump. Do not sign any contract or start any work before obtaining confirmation of your subsidy application. Ensure that the location of the outdoor unit respects regulatory distances and noise limits for your neighbors.
Check if renovation of insulation is more cost-effective than buying an overpowered heat pump.
Before requesting quotes, check if your area is connectable to district heating. Prepare a complete file including your house plans and energy bills from the last few years. Always request several comparable quotes to evaluate the different technical solutions offered by installers.
Confirm that the installer includes administrative procedures and compliance with RLE standards in their service. Finally, ensure you fully understand the operation and maintenance needs of the proposed model.
Flat amounts depending on heat pump type (air-water, ground-source).
Support from the canton of Fribourg and the Buildings Programme for heat pumps replacing fossil fuels.
www.leprogrammebatiments.chCheck amounts and conditions with the provider before signing: apply before work starts in most cases.
1752 Villars-sur-Glâne · about 0 km
Villars-sur-Glâne-based company specializing in maintenance, repair, and renovation of sanitary and heating systems.
jentretiens.ch1752 Villars-sur-Glâne · about 0 km
LEATECH SA provides technical maintenance and operation of HVAC, plumbing, electrical and refrigeration systems, alongside building caretaking and surveillance, in French-speaking Switzerland.
leatech.ch1752 Villars-sur-Glâne · about 0 km
Villars-sur-Glâne based company specializing in sanitary installations, heating, water treatment, and emergency repairs.
solutechnique.ch1752 Villars-sur-Glâne · about 0 km
Polymaintenance SA offers maintenance, repair, and renovation services for sanitary and heating systems.
polymaintenance.chSuggestions from the commercial register by distance and activity. Not an endorsement or partnership.
No, you must respect property boundary distances and be mindful of noise levels for your neighbors. It is advisable to consult the municipality to validate the exact location.
Gather your heating bills from the last three years to provide an average to your heating engineer. This will allow them to correctly size the heat pump.
Yes, if it is correctly sized according to the -9.3 °C temperature. A technical study ensures its efficiency even during the 96 annual frost days.
Yes, replacing fossil fuels requires a renewable energy share of at least 10%. Exceptions exist only for very specific and unforeseeable cases.
Yes, expenses related to energy efficiency are deductible. You can carry over the surplus to the two following tax periods.
It is highly recommended to validate your project with the municipality and submit your subsidy application before signing any commitment.
It depends on your location. Check with Groupe E if your plot is connectable, as this can be an efficient alternative without an outdoor unit.
Source : swisstopo – service d'altitude (MNT)
Source : Open-Meteo Historical Weather API (réanalyse ERA5, moyenne 2015-2024)
Source : Open-Meteo Historical Weather API (réanalyse ERA5, moyenne 2015-2024)
Source : Open-Meteo Historical Weather API (réanalyse ERA5, moyenne 2015-2024)
Source : Open-Meteo Historical Weather API (réanalyse ERA5, moyenne 2015-2024)
Source : Open-Meteo Historical Weather API (réanalyse ERA5, moyenne 2015-2024)
Source : Open-Meteo Historical Weather API (réanalyse ERA5, moyenne 2015-2024) · estimate
Source : Groupe E
Source : fr.ch
Source : Commune de Villars-sur-Glâne
Source : Administration Cantonale des Impôts du Canton de Fribourg