Facade insulation – Oron

At a glance

Typical budget
CHF 36'800 – CHF 73'000
Midpoint
CHF 52'800
Grants found
1
Nearby companies
4

Worked examples in Oron

Small project

CHF 20'000 – CHF 41'400

Typical project

CHF 36'800 – CHF 73'000

Large project

CHF 62'100 – CHF 120'400

ProjectQuantityLowHigh
Small project110 m²CHF 20'000CHF 41'400
Typical project220 m²CHF 36'800CHF 73'000
Large project385 m²CHF 62'100CHF 120'400

Computed with our estimator for Oron (regional factor included), standard finish. Only the project size changes.

Cost split (typical project)

  • Labour : CHF 26'400 (50 %)
  • Materials : CHF 21'100 (40 %)
  • Other costs : CHF 5'300 (10 %)

What the price covers

Included

  • Supply and installation
  • VAT
  • Scaffolding, finish and insulation according to answers

Not included

  • Permits and architect fees
  • Unexpected structural issues
  • Possible subsidies
  • Structural damp, asbestos and balcony alterations

Tips before you start

  • A grant application must usually be filed before work starts.
  • External insulation changes the building's look and often needs a permit.
  • Scaffolding is a big share of the cost: bundle facade, windows and roof.

Your project in 5 steps

  1. 1. Estimate

    Set a budget range with the estimator.

  2. 2. Grants

    Apply before work starts.

  3. 3. Quotes

    Compare at least 3 quotes.

  4. 4. Permit

    Check with the municipality whether a permit is needed.

  5. 5. Works

    Follow the site and do a written handover.

Grants and subsidies

Canton

Facade insulation — Buildings Programme (VD)

Contribution per insulated m², depending on energy requirements met.

Grants for thermal insulation of the building envelope (walls, roof) via the Buildings Programme.

www.leprogrammebatiments.ch

Check amounts and conditions with the provider before signing: apply before work starts in most cases.

Oron's housing stock in figures

The federal building register lists 1'234 residential buildings with 2'912 dwellings in Oron. 58% were built before 1980, before serious insulation standards, and 54% are still heated with oil or gas.

With 58% of buildings dating from before 1980, the envelope is often the biggest saving. 79% are one- or two-dwelling houses where the owner decides alone; in apartment buildings, plan for a co-owners' decision. Have asbestos and PCB checked first.

58 %built before 1980
54 %heated by oil or gas
23.1 %electric hot water
15.6 %with declared solar thermal

Age of residential buildings

  • Before 191935 %
  • 1919–19455 %
  • 1946–19605 %
  • 1961–19707 %
  • 1971–19806 %
  • 1981–199011 %
  • 1991–20006 %
  • 2001–201012 %
  • Since 201114 %

Main heating energy

  • Heating oil41 %
  • Heat pump24 %
  • Gas13 %
  • Electricity11 %
  • Wood11 %

Houses or apartment buildings?

  • Single-family houses63.9 %
  • Two-dwelling houses15.1 %
  • Apartment buildings (3+)21.1 %

17.8 % of buildings mix housing with shops or offices.

The typical building

storeys (median)
3
median footprint
135 m²
median dwelling area
95 m²

Renovations, heritage and volumes

For your renovation projects in Oron, RegBL figures provide vital guidance. With 7 protected heritage buildings among 98 known, you should contact the municipality early to discuss permits; please note that heritage data coverage is partial. Regarding house volume, the median is 884.5 m3 based on the SIA 416 standard, calculated from 248 out of 788 houses. This figure is essential for estimating the scale of heating and insulation upgrades. Be aware that data coverage for building volume in this municipality remains partial, as many units are not yet measured under this specific standard.

7
buildings flagged as protected
status known for 98 of 1'234 buildings; check with the municipality
884.5 m³
median house volume (SIA 416)
measured for 248 of 788 houses

Source : OFS — RegBL (export communal complet). Existing residential buildings; percentages of recorded values.

Companies in the area

Crémat SA

1607 Palézieux · about 0 km

Crémat SA is a company specializing in lifting, handling, and facade renovation services.

cremat.ch

James Enveloppe du Bâtiment Sàrl

1607 Palézieux · about 0 km

Specialist in tinsmithing, roofing, waterproofing, and ventilated facades based in Palézieux, with over 40 years of experience.

enveloppe-du-batiment.ch

Sonnay Charpentes SA, succursale de Palézieux

1607 Les Tavernes · about 0 km

Fribourg specialist active since 1996 in carpentry, roofing, interior and exterior woodwork, as well as window and shutter installation.

sonnay-charpente-romandie.ch

Gregorio Toiture Sàrl

1607 Palézieux · about 0 km

Gregorio Toiture Sàrl, based in Palézieux, specializes in roofing, sheet metal work, waterproofing, and the installation of solar panels.

gregoriotoiture.com

Suggestions from the commercial register by distance and activity. Not an endorsement or partnership.

Useful local data

Rules of the canton of Vaud

These rules apply across the whole canton, not only in this town.

Permits

  • Legal basis : LATC et RLATC (BLV 700.11 et 700.11.1)
  • Competent authority : Commune concernée, avec consultation des services cantonaux selon le projet
  • Heat pump : Pour certaines pompes à chaleur desservant un bâtiment existant, une procédure d’annonce est prévue par l’article 68c RLATC, sous conditions. Si les conditions ne sont pas remplies, une procédure de permis de construire est nécessaire. Vérifiez votre cas auprès de la commune.
  • Procedure : La procédure dépend de la nature des travaux et de la situation du bâtiment ; la commune confirme la procédure applicable.

Source : État de Vaud — Permis de construire (LATC / RLATC)

Tax deductions

  • Note : Le contribuable peut choisir, lors de chaque période fiscale et pour chaque immeuble, entre la déduction des frais effectifs et la déduction forfaitaire. La déduction forfaitaire couvre les frais d'entretien, de remise en état d'immeubles acquis récemment, d'administration par des tiers, d'investissements énergétiques, de démolition et de primes d'assurances.
  • Carry-forward : Si les coûts d'investissement destinés à économiser l'énergie et à ménager l'environnement ou les frais de démolition en vue d'une construction de remplacement ne peuvent pas être entièrement pris en considération fiscalement durant l'année où ils ont été engagés, le solde peut être reporté sur les deux périodes fiscales suivantes. Les dépenses peuvent être reportées si le revenu net est négatif. Si des frais sont reportés, il n'est pas possible de faire valoir une déduction forfaitaire pendant cette période fiscale. En cas de déménagement en Suisse ou de transfert de la propriété de l'immeuble, le contribuable conserve le droit de déduire le solde des frais pouvant être reportés.
  • Maintenance costs : Le contribuable qui possède des immeubles privés peut déduire les frais nécessaires à leur entretien, les primes d'assurances relatives à ces immeubles et les frais d'administration par des tiers.
  • Energy investments : Sont réputés investissements destinés à économiser l'énergie et à ménager l'environnement les frais encourus en vue de rationaliser la consommation d'énergie ou de recourir aux énergies renouvelables. Ces investissements concernent le remplacement d'éléments de construction ou d'installations vétustes et l'adjonction d'éléments de construction ou d'installations dans des bâtiments existants. Si les mesures sont subventionnées par la collectivité publique, le contribuable ne peut déduire que les frais qu'il assume lui-même. Le taux de déduction est de 100%.

Source : Règlement sur la déduction des frais relatifs aux immeubles privés (RDFIP)

Other works in Oron

Facade insulation in nearby towns